​​​​​​ ​​​​​​​Natural Gas Line Upgrades in Deephav​en​

We are committed to keeping our customers informed about important updates we are making to our infrastructure – designed to enhance safety, improve reliability, and continue to provide you with the energy you need for life's moments.

Project Resources ​​​

Sign up for updates in Deephaven

Overview

Minnetonka Blvd

Starting as early as March 30, 2026, CenterPoint Energy and authorized contractors will upgrade the natural gas infrastructure along Minnetonka Blvd. This work may last up to 6 weeks.​ 

Deephaven work area

If you are having trouble viewing the map, right-click the image and select "open image in new tab". 


Cottagewood Rd and Minnetonka Blvd

Starting as early as April 13, 2026, CenterPoint Energy and authorized contractors will upgrade the natural gas infrastructure along Cottagewood Rd and Minnetonka Blvd. This plastic and steel work may last up to 16 weeks. ​Work area will be closed to through traffic - residents will continue to have access, crews will coordinate. 

May 2026 Update:​

Phase 1: A road closure will be in place from Carsonwood Ave to Minnetonka Blvd (just north of Deephaven Elementary School). This work area may take up to 6 weeks. ​

Phase 2: Following this, crews will work south onto Vine Hill Rd and through Cottagewood Rd. This work area may last through ​August. 



If you are having trouble viewing the map, right-click the image and select "open image in new tab". 


Heathcote Rd Area

Starting around May 18, 2026, CenterPoint Energy and authorized contractors will upgrade the natural gas infrastructure surrounding Heathcote Rd. This work may last up to 4 weeks.​​​

Closure from above work area will be in place, residents will continue to have access.  ​



Contractor summary 

CenterPoint works with multiple contractors to complete construction projects in a safe and timely manner. You will see these contractors working in your area and may be contacted by them at various stages of the construction process. Employees of authorized contractors will have CenterPoint identification cards. You are encoura​ged to ask to see identification before allowing technicians inside your home.

Marking utilities  

CenterPoint Energy will locate public underground utilities. This is an important safety preparation, done before construction begins. The utilities will be marked with spray paint and flags. 

If you have installed any private lines such as sprinklers or dog fences, we ask that you mark them with a material that is convenient for you. Examples include spray paint, flags, and wooden sticks used to stir paint. Marking sprinkler heads is sufficient. If any utility flags are left in residents' yards after restoration is complete, they may be removed and thrown away. 

Natural gas main work

To increase the safety and reliability of CenterPoint's gas distribution, natural gas mains are replaced with modern piping. Main is replaced by either boring underneath one side of the road or trenching in the road. Please keep in mind that some intersections may not be permanently restored until after the work is complete. Until then, customers may see temporary backfill such as dirt or gravel.

Service line and meter work  

After completing main work, service line work can begin to connect your property to the main. CenterPoint will send notice before the service crew arrives on site. For most properties, the crews remove at least one sidewalk panel in front of the house, excavate a hole by the outside meter and bore the service line from the sidewalk to the house. 

Customers with outside meters will be notified prior to the meter's replacement or connection of their service lines to the new main, and a technician will schedule appointments to relight the gas service on each property. The crew will also make appointments with residents to move inside meters outside. ​

Visit the Construction Definitions page for more information. 

Restoration  

The final step in an infrastructure project is to restore the areas that may have been impacted by construction. Restoration is typically on site for a few weeks after the completion of other construction activities. Until then, temporary restoration is done by the utility crews. For more details visit the Restoration Practices page. 

Traffic impacts  

Most traffic impacts will be restrictions on street parking, closure of one sidewalk at a time, and lane shifts. Crews will work with owners on maintaining access to and from their property. Additional traffic impacts and road closures will be communicated as they are in place. ​

Additional Resources 

If you have questions, reach out to CenterPoint Energy's Communication Specialist at 612-542-6198 or MNconstruction@centerpointenergy.com

 

Thank you for your patience and understanding as we replace our infrastructure! We value the privilege of having you as a customer.