​​​Minneapolis – Morris Neighborhood


Anticipated timeline: Several weeks beginning mid-November 2024

CNP Map of Minneapolis Morris 8.13.24.png 



  • If you contact CenterPoint Energy, please reference the project’s work order number 112803192

 

Overview

In 2023, CenterPoint Energy moved inside meters outside in Morris Neighborhood on select streets between 55th Street E. and 58th Street E. and between 34th Avenue S. and 42nd Avenue S.

 

For a few months in late August 2024, CenterPoint Energy's authorized contractors made important upgrades to CenterPoint's natural gas infrastructure in the Morris Neighborhood of Minneapolis.

 

This November, beginning Tuesday, Nov. 12, a crew from Michels Corporation will begin installing a natural gas main under the east sidewalk of 42nd Avenue S. between 54th Street E. and 55th Street E. Following the installation of the new main, another crew will move inside meters outside by appointment and replace and/or reconnect service lines to the new main. Restoration will follow in the path of service work, approximately 2 weeks behind.

 

Equix Integrity updates our records on the locations of sewer lines in relation to natural gas lines. Michels Corporation will work on the natural gas lines. Q3 Contracting will restore the areas affected by Michels Corporation's work. 

 

The pipes used in these pipeline replacement and modernization projects are more resistant to corrosion and leakage, helping us continue to provide the safe, reliable service you count on that keeps you comfortable in your home. There will be no assessment or cost associated with our work.​


Marking u​tilities

CenterPoint Energy will contact Gopher State One Call 811 to locate public underground utilities such as water, sewer, and cable. You will see markings such as spray paint and utility flags. They will be color-coordinated to indicate a separate utility.

If you have installed any private lines such as sprinklers or dog fences, we ask that you mark them with whatever material is convenient for you. Examples include spray paint, flags, and wooden sticks used to stir paint. Marking sprinkler heads is sufficient.

If any utility flags are left in residents’ yards after the natural gas work and the restoration work is done, and the crew do not remove the flags, residents can remove the flags and throw them away.


Traffic impa​cts

Most traffic impacts will include parking closed on both sides of the road and one sidewalk closed at a time with the opposite sidewalk open.


Natural gas main work

The crew plans to bore the main underneath the east sidewalk on​ 42nd Avenue S. from 54th Street E. to 55th Street E.
Please keep in mind that some intersections or some sidewalk panels at intersections may not be permanently restored until after the service line work is done. After all customers’ service lines are transferred to the new main, the crew can connect the new main to the existing intersecting mains and put the new main into service. Then the restoration crew will permanently restore these areas. Until then, customers may see temporary backfill such as dirt or gravel. We thank you for your patience!

Service line and meter work

The customer will receive a CenterPoint Energy postcard in the mail explaining the project before the natural gas crews perform the work. The crews will have CenterPoint Energy-authorized photo IDs. After the customer receives the postcard, the technician will arrive at the customer’s house to schedule an appointment that typically meets with the customer’s schedule. If the customer isn’t home when they arrive, they will leave a door tag with their contact information to schedule an appointment with them.

One natural gas crew typically works on about one block per week. They will either fully replace the service line or reconnect it to the new main, depending on the line’s age. For most properties, the crews remove at least one sidewalk panel in front of the house, excavate a hole by the outside meter, and bore the service line from the sidewalk to the house.

For inside meters, the crew will make a two- to three-hour appointment at a time that works with the resident. We encourage customers to work with the crew on where they want the meter to go, keeping limitations in mind such as a minimum of three feet away from areas such as windows, doors, and vents. Customers with outside meters will be notified prior to the replacement or connection of the service lines to the new mains.

The technician will access the natural gas meter inside the house, move the meter outside, and relight the natural gas appliance pilot lights after the new meter has been relocated.


Restoration

After the service line and meter work, the gas crew will backfill the excavated areas with dirt or gravel. This will be temporary before the restoration crew comes. On boulevards and lawns, they will refill the areas with black dirt, grass seed, and netting made of wood fiber that degrades over about four months. Prior to mowing the restored area, remove any loose staples that secured the netting. For photo examples, please visit our Restoration Practices page.

We hope to minimize the disruption as much as possible. Thank you in advance for your patience and understanding as we replace our infrastructure. We wish you a great season.