Minneapolis – Fulton Neighborhood
Anticipated timeline: Several weeks starting mid-October 2024
- If you contact CenterPoint Energy for any questions, please reference the project’s number
113097920.
Overview
For several weeks starting in mid-October or another time to be determined in fall 2024, CenterPoint Energy’s authorized contractors will work in the Fulton and the Kenny Neighborhoods in Minneapolis to upgrade portions of CenterPoint’s natural gas infrastructure. The crews will work along Zenith Avenue S. between 49th Street W. and 52nd Street W.
Equix Integrity updates our records on the locations of sewer lines in relation to natural gas lines. Michels Corporation will replace the natural gas plastic mains, move inside meters to the outside of homes by appointment, and replace and/or reconnect natural gas service lines to the new mains. Q3 Contracting will restore the areas affected by Michels Corporation’s work. There will be no assessment or cost associated with our work. Although traffic plans are to be determined, please expect parking closures.
The pipes used in these pipeline replacement and modernization projects are more resistant to corrosion and leakage, helping us continue to provide the safe, reliable service you count on that keeps you comfortable in your home.
Marking utilities
CenterPoint Energy will contact Gopher State One Call 811 to locate public underground utilities such as water, sewer, and cable. You will see markings such as spray paint and utility flags. They will be color-coordinated to indicate a separate utility. If you have installed any private lines such as sprinklers or dog fences, we ask that you mark them with whatever material is convenient for you. Examples include spray paint, flags, and wooden sticks used to stir paint. Marking sprinkler heads is sufficient.
Natural gas main work
The crew plans to bore the main underneath the east sidewalk from 49th Street W. to 50th Street W. and under the west sidewalk from 50th Street W. to 52nd Street W.
Please keep in mind that some intersections or some sidewalk panels at intersections may not be permanently restored until after the service line work is done. After all customers’ service lines are transferred to the new main, the crew can connect the new main to the existing intersecting mains and put the new main into service. Then the restoration crew will permanently restore these areas. Until then, customers may see temporary backfill such as dirt or gravel. We thank you for your patience!
Service line and meter work
The customer will receive a CenterPoint Energy postcard in the mail describing the project before the natural gas crews perform the work. The crews will have CenterPoint Energy-authorized photo IDs. After the customer receives the postcard, the foreman will arrive at the customer’s house to schedule an appointment that typically meets with the customer’s schedule. If the customer isn’t home when they arrive, they will leave a door tag with their contact information to schedule an appointment with them.
One natural gas crew typically works on about one block per week. They will either fully replace the service line or reconnect it to the new main, depending on the line’s age. For most properties, the crews remove at least one sidewalk panel in front of the house, excavate a hole by the outside meter, and bore the service line from the sidewalk to the house.
For inside meters, the crew will make a two- to three-hour appointment at a time that works with the resident. We encourage customers to work with the crew on where they want the meter to go, keeping limitations in mind such as a minimum of three feet away from areas such as windows, doors, and vents.
Customers with outside meters will be notified prior to the replacement or connection of the service lines to the new mains. The technician will access the natural gas meter inside the house, move the meter outside, and relight the natural gas appliance pilot lights after the new meter has been relocated.
Restoration
After the service line and meter work, the gas crew will backfill the excavated areas with dirt or gravel. This will be temporary before the restoration crew comes. On boulevards and lawns, they will refill the areas with black dirt, grass seed, and netting that degrades over about four months. Prior to mowing the restored area, remove any loose staples that secured the blanket.